The ICT VINA III Manufacturing Plant Project – Phase 1 is progressing on schedule and showing positive signs in construction progress. Reaching the 70% completion milestone not only affirms strong project organization and management capabilities, but also demonstrates the firm commitment of the design and build general contractor, Dinco E&C, to ensuring quality, timeline, and safety in strict accordance with the Investor’s requirements.
Construction Progress Closely Aligned with the Planned Schedule
To date, several key components of the project have been fully completed, including the FM1 concrete flooring, steel structure, and roofing works. These foundational elements play a critical role in shaping the overall structural framework of the facility, providing a solid base for the subsequent phases of construction.
.jpg)
At the same time, the remaining works are being carried out in parallel and accelerated to maintain overall progress. Specifically, masonry and plastering, installation of external and internal panel walls, and infrastructure works are being prioritized with focused resource allocation to ensure on-schedule completion. The application of well-structured construction planning, combined with stringent quality control at every stage, has enabled the project to sustain a steady pace while minimizing potential risks.
Entering the Finishing Phase – Ready to Accelerate
With the completion of major components, the ICT VINA III Project – Phase 1 has now entered the finishing stage. This phase requires a high level of precision and close coordination between construction and supervision teams to ensure overall consistency and the highest quality standards of the project.
.jpg)
During this phase, the entire team of engineers, managers, and workers is mobilizing maximum resources and accelerating construction efforts to meet critical milestones. At the same time, strict adherence to occupational safety and environmental standards is being maintained, ensuring efficient and sustainable site operations.
Commitment to Quality, Schedule, and Safety
Achieving 70% completion marks a significant milestone, signifying the project’s transition from structural works to the finishing stage. This accomplishment also reflects the contractor’s professional construction capabilities, strong sense of responsibility, and effective coordination among all stakeholders involved.
In the coming period, the project will continue to be executed with the goal of completing and handing over on schedule, fully meeting all technical standards and the stringent requirements of the Investor. Commitment to quality, timeline, and safety will remain the guiding principles throughout the entire project execution.