HOW IS THE PROJECT OF “VN DANANG - RENTAL BUILDING HALL 3 ELECTRIC - DRAEXLMAIER AUTOMOTIVE – PHASE 2” CURRENTLY?
By the end of July 2022, the project has completed 53% of the work volume (while only 45% of the time has passed). The team has completed the renovation of the roof ventilator of the Hall 3 Factory, and the reinforcement of the existing roof of Hall 3.


HAPPY DUNG QUAT PROJECT - PHASE 4 AHEAD THE CONSTRUCTION PROGRESS
Up to now, the project has been implemented for 4 months, the Site Management Board of Happy Dung Quat - Phase 4 project has completed 80% of the work. Dinco is rushing to implement the final works such as concrete pouring, workshop foundation, and steel work. With the current progress, Dinco is confident to finish the project 1 month earlier than contracted but still ensure the highest quality.


SANGSHIN CENTRAL VIETNAM PROJECT FOR ACHIEVING THE SAFETY CERTIFICATE
Congratulations on SangShin Central VietNam project for achieving the safety cerificate of June 2022.


VIDEO OF CONSTRUCTION PROGRESS OF CHAN MAY QUARTZ MACHINING FACTORY IN HUE AFTER 1 MONTH OF COMMENCEMENT
Video of Construction progress of Chan May Quartz Machining Factory in Hue after 1 month of commencement. Update on 01.06.2022.


GROUND-BREAKING CEREMONY OF SANGSHIN CENTRAL VIETNAM PROJECT
In the morning of June 1, 2022, at Ai Tu commune, Trieu Phong district, Quang Tri province, Dinco Engineering and Construction Corporation solemnly held the Groundbreaking Ceremony of Sangshin Central Vietnam project.


HOW IS THE PROGRESS OF HAPPY FURNITURE PHASE 4 PROJECT?
Happy Furniture Phase 4 project was started by Dinco General Contractor on February 11, 2022 and expected to be completed on August 31, 2022.